2024 12 01 Logging
Good Sunday Morning Everyone!
Today is Sunday, December 1, 2024, 6:00 am MST. At report time, we are currently TIH with a bit and reamer BHA, circulating and conditioning mud as we TIH.
Yesterday we finished POOH and rigged up Schlumberger. We made one run (out of a proposed 4 runs) and started POOH with tools when mechanical issues developed with the logging truck.
Spent several hours trying to resolve the issue without success.
Decision made to change out logging truck. The replacement truck will not be on location until Sunday afternoon.
A decision was made to TIH with bit and reamer to condition the hole and mud system.
We had a good logging run #1, however; no results or conclusions are available yet, and the data has yet to be processed.
Current bit depth 12,600’ MD (bottom of 7” casing at 12,670’ MD.
Circulating and conditioning mud system.
Current plans are:- Finish TIH with reamer BHA to 15,712’ MD TD
- POOH
- Finish running open hole logs
- TIH with bit & drill pipe
- Circulate and condition mud to run 4½” casing.
- POOH LDDP (“Pull Out Of Hole Lay Down Drill Pipeline")
- Run 4½” production casing
- Cement
- RDMO Rig 88 to Jeffrey City yard.
Estimated 8 to 10 days remaining on location.
Today’s video topic focuses on open hole logging. You get some great views of what really goes on inside of the logging truck.
Great job Jacek!!
Also attached is a picture/panorama of another sunset on Rig 88.