Lots of operations have been happening out here on the Wild Mustang Federal Unit!
During the week of September 18th to 22nd, completion operations were conducted on the Green Mountain Federal #4 (“GMF4”) and the Found Soldier Federal #1 (“FSF1”).
On Thursday, September 11, 2025, both wells were successfully fracture stimulated and shut in for 24 hours to allow the frac fluid gels to break and Liberty Pumping Services to RDMO (“Rig Down Move Out”).
Both wells were fraced with a total of 341,000# of sand and 435,000 gallons (10,357 Bbls) of gelled water and sand.
The wells were opened up on Friday, September 12th, through test separators to recover and measure all load water and frac fluids.
Please see the links below to videos for all operations to date.
The videos will speak for themselves!
More to follow............
Thank you for your investment in Lost Soldier Oil and Gas !!
2025 08 11 https://vimeo.com/1109813447/fd18f19708?share=copy
2025 08 11 Drilling Water Well #1
2025 08 21 https://vimeo.com/1114052782/eb459cf956?share=copy
2025 08 21 Completion Operations Found Soldier Federal #1 &
Green Mountain Federal #4
2025 09 11 https://vimeo.com/1118617393/2d520fd15c?ts=0&share=copy
2025 09 11 Fracing Operations - Found Soldier Federal #1 and Green Mountain Federal #4
2025 09 12 https://vimeo.com/1118618588/ef56050284?share=copy
2025 09 12 Flaring GMF#4 and FSF #1 (Post Frac)