Good Morning Everyone!

Today is Sunday, December 8, 2024, 6:00 am MST. At report time, we have finished running and successfully cementing the 4½” OD production casing!
Bumped the plug at 6:00 am MST. Held 3,500 psi on casing for 30 minutes.
Bottom of the casing is set at 15,707’ MD (15,712’ TD).
Great job Ben and Duane!!

The video below was previously sent on 11/16/2024.
It is a great animation of running and cementing casing in a vertical well.

2024 11 16   https://vimeo.com/1030347320/8a045ee350?share=copy

2024 11 16 Vertical Gas Well Drill and Complete



Current plans are:
  1. Drop slips and hang casing off in wellhead.
  2. ND (“Nipple Down”) BOP stack
  3. Haul off mud and clean pits
  4. RDMO Rig 88 to Jeffrey City yard.

Today’s video features Part 2 of the coring video.
Steve Richards explains more of the technical aspects of the process.

Also, today’s attached pictures feature Jacek Bogucki, videographer, at his finest hour!
Jacek is responsible for all the great videos and still pictures in previous emails.
Thank you, Jacek, for your great work!!
 

Enjoy!!

 