Join the room, call it "AJ Daily"

Join like a ZOOM MEETING 🖥 😎 AJ Daily @ noontime PST

We can even talk about "Big Oil and Gas Development"

Big Oil and Gas 24

About Me

My photo
When discussing the future of the oil and gas industry beyond 2024, it is important to consider the unscientific use of the propaganda term "pollutant" when referring to CO2 gas. While people often label CO2 as a "Greenhouse Gas", it's important to remember that CO2 is necessary for all plant life, and mammals exhale CO2 as a natural part of their bodily functions. Therefore, labeling CO2 as a pollutant is wrong. Do Not Comply if necessary, California government officials could be informed of these facts.

Followers

CO2?

When discussing the future of the oil and gas industry beyond 2024, it is important to consider the unscientific use of the propaganda term "pollutant" when referring to CO2 gas. While people often label CO2 as a "Greenhouse Gas", it's important to remember that CO2 is necessary for all plant life, and mammals exhale CO2 as a natural bodily function. Therefore, labeling CO2 as a pollutant is wrong. Do Not Comply if necessary, California government officials should be informed of these facts.

Oil Patch 2024

Oil Patch 2024
Oil Patch 2024



Friday, November 1, 2024

 This morning, Friday, November 1, 2024, 6:00 am MST, we are still washing and reaming our way back in the hole with a new bit and BHA (“Bottom Hole Assembly”). 10,785’ TD. We did not make any hole again yesterday due to the bit trip. While TIH, we tagged fill in the hole and started to wash and ream our way back to bottom. The hole had started to sluff in on us causing these conditions. The hole is becoming more stable as we increase the mud weight. We are currently washing and reaming @ 10,635’, almost back to TD at 10,785’. The hole is stable and in much better condition than previously anticipated. Plans are to: (1.) circulate the mud system, raising the mud weight to an even 10.4 ppg all around, both in the hole and in the pits, (2.) POOH, (3.) replace standpipe and related equipment increasing the working pressure on the mud system from 5,000 psi to 7,500 psi. With the increased mud weight and depths, being restricted to 5,000 psi working pressure is causing lower P rates. When we get back to bottom with the new bit and BHA, P Rates should be substantially higher. The estimated intermediate casing depth is 12,800’. The last couple of days is a perfect example of the previously mentioned oilfield saying, “Let the hole tell you what to do”. This was the hole telling us “You better raise the mud weight or I’m going to fall in on you!!”. The hole is stabilized now……..
 Today’s video features Mr. John Kennedy, one of the Rig Managers for Rig 88. Mr. Kennedy has been in the oilfield for over 25 years and has an extensive family history. He has been with Earl Sanford for most of those 25 years both in the domestic United States and internationally. There are four Rig Managers for Rig 88. Two Rig Managers are always on the rig working 12-hour shifts. Two are always on days off. During their respective tour, Rig Managers are responsible for all rig personnel, rig functionality, maintenance, and repairs. A big job, indeed! They spend most of their time talking and conferring with all rig personnel to ensure safe, efficient operations. A big job, indeed! In the video, you can see John conferring with Cody Davis, one of the previously interviewed Drillers. They are closely watching and monitoring the drilling parameters in the doghouse on the floor to maximize P rates. The level of technologies available nowadays to drilling personnel is truly amazing. Watch the screen closely towards the end of the video. 


2024 11 01 Profiles of Courage - John Kennedy (Rig Manager)

No comments:

Post a Comment

2024 11 12 Profiles of Courage - Joshua Mitchell (Mudlogger)

2024 11 12 Profiles of Courage - Joshua Mitchell (Mudlogger)   This morning,   Tuesday, November 12, 2024 , 6:00 am MST, we are running open...